Scope of work
(Phase 1):
- Early
Production activities (part of Phase-1):
-
3D seismic interpretation.
-
Reservoir study – modeling and updating.
-
Drilling and completion of one (1) main Ilam producer well
(new).
-
Work over two (2) of the existing wells.
-
Logging, coring, PVT sampling, well test, similar to activities
which are mentioned in appraisal well program, should be
carried out in the appraisal well (JR-4) drilling of which is in
progress now. If any part of the above mentioned activities down
to the base of Sarvak oil zone could not be achieved in the well
JR-4, it would be implemented in the new producer well (item 3
above). The appraisal well will be completed as an oil producer.
-
Construction of 40 KM pipelines (6" flowline & 10" pipeline),
header and installation of metering system for fluid measurement
to use as custody meter
-
Environmental Baseline Study (EBS) and Environmental Impact
Assessment (EIA).
-
Reservoir study – models updating.
- Drilling
and completion of eight (8) oil producers (including Early
Production wells).
- Workover
three (3) of 4 existing wells (including early production
wells).
-
Facilities Front End Engineering and Design (FEED).
-
Construction and installation of oil flowlines, oil and
associated gas and water processing facilities and utilities,
oil transfer and water disposal pipelines.
-
Construction of buildings such as Tehran/Ahwaz offices,
temporary and permanent camp, warehouse, workshop, security,
transportation, medical and sport.
- Studies
related to Improved Oil Recovery/Enhanced Oil Recovery (IOR/EOR)
application.
Scope of work
(Phase 2):
-
Environmental Baseline Study (EBS) and Environmental Impact
Assessment (EIA).
-
Reservoir study – models updating.
-
Facilities Front End Engineering and Design (FEED).
-
Drilling and completion of five (5) oil producers.
-
Workover one (1) of 4 existing wells to water disposal.
-
Construction and installation of oil flowlines, oil and
associated gas processing facilities, oil transfer line to
Ahwaz Booster Station (ABS), local power plant and
re-injection facilities of disposal water.
-
Construction of water supply and disposal water pipelines
-
Studies related to Improved Oil Recovery/Enhanced Oil
Recovery (IOR/EOR) application.
Objectives (Stage 1):
- To
achieve an Early Production level of 6,000* STBO/day within 13
months from effective date.
- To
achieve 1st Production level of 15,000 STBO/day within 31 months
from effective date.
- Evaluate
EOR/IOR and unproved area development options and proposes the
optimum development plan.
Objectives (Stage 2):
- To
achieve 2nd Production level of 25,000 STBO/day
within 63 months from effective date.
- Evaluate
IOR/EOR and unproved area development options and proposes the
optimum development plan.
|
Contract Price and Duration :
-
Early production activities duration is 13 months from
effective date.
-
Phase-1 development duration is 31 months from effective
date.
-
The buyback project contract price:
- Early Production Activities price is 72 MMUSD (lump
sum).
- Phase-1 (capex) shall be specified after receiving bids.
- Phase-2 (capex) shall be specified after receiving bids.
|
|