Scope of work :
-
Collecting, certifying and interpreting data, preparing
reservoir models, and proposing the strategy for optimum
development of the field.
-
Drilling and completing 6 new horizontal wells
( 3 multilaterals and 3 single producers ).
-
Drilling and extending the open hole section of the
existing well.
-
Construction of a wellhead platform.
-
Providing production facilities including Floating Production
Storage and Offloading (FPSO) vessel, mooring system and
flexible pipe to transfer crude oil from wellhead platform to
the FPSO vessel.
Objectives
:
-
Production of up to 35,000 bpd of crude oil in the 1st development
phase.
-
Evaluating production enhancement of the field, and identifying
new producing layers.
-
Appraising the field and evaluating the possibility of the 2nd
phase development.
Achievements:
Status:
30.5% physical progress (including the additional works and
updating the weight factors for calculating project progress)
·
Sub-surface Studies
o
Updated production forecast based on reservoir model updates
using information obtained from drilling.
o
Full field reservoir static and dynamic models were
developed and later
revised with latest available data.
o
Finalized depth structure map of reservoirs
·
Drilling Operations
o Drilling
six new wells through the sub sea drilling template
o Compiling
completion and drilling equipment list required for the tie-back
and completion operation
o
Preparing preliminary drilling schedule for completion phase.
·
Offshore surface facilities
o
The engineering design contract for the W.H.Platform was awarded
to a contractor(Tecnomare) and the work was completed on
December 2006.
o
The received proposals of FPSO Providers are under evaluation
and discussion.
o
The platform's jacket fabrication was started by WHP ePCI
contractor (SAFF).
o
The pipeline engineering is completed.
|