Project Name :

Integrated Appraisal and Development Operations of Azadegan Field (Azadegan Oil Field Development)

Location :

Azadegan field is situated in 100 km from large population centers: Ahwaz and Abadan.

Scope of work (Stage-1):

  • The reservoir model by incorporating the 3D seismic data.
  • Drilling and Completion of 2 key producer wells with appraisal objectives.
  • Drilling and Completion of 36 production wells (including the 2 key producers) and 1 water disposal well.
  • Extended Well Testing (EWT) to be started once minimum facilities (wells, flow-lines, separators, and pipelines, etc.) are ready for producing crude oil.
  • Construction and Installation of flow-lines and production facilities with a sustainable capacity of 150,000bbl/day / 135 MMscfd to deliver oil and gas.
  • Construction of gas-lift system, including gas treatment, compression and in-field pipe network for the north heavy oil reservoir wells.
  • Construction and installation of oil pipeline to transport processed oil to NIOC’s booster station in Ahwaz.
  • Construction and installation of gas pipeline to transport dehydrated gas to NIOC’s tie-in point near Ahwaz NGL-600.
  • Construction and installation of power generation plant and fresh water import pipeline/treatment facilities to support oil and gas production.
  • Provision of all the support (offices, accommodation, logistics, infrastructure, etc.) required for the Field development and production.
  • Studies on Enhanced Oil Recovery (EOR) application.
  • Operation of the EWT until 18 months after Commencement of EWT or First Production, whichever comes first.
  • Construction of elevated well-pads and access roads.

Objectives (Stage-1):

  • Within 40 months from the Effective Date (ED), reach the Extended Well Test milestone by establishing production of 50,000 bbl/day. Deliver oil produced from Extended Well Test to Ahwaz Booster Station.
  • Within 52 months from ED, reach the First Production milestone by establishing a production level of 150,000 bbl/day. To achieve the production level of 150,000 bbl/day, the production rate of 70,000 bbl/day – 100,000 bbl/day is planned from the heavy oil reservoir and 50,000 bbl/day – 80,000 bbl/day from the light oil reservoirs.

Achievements:

  • General
    • Armor clearance has been completed.
    • Environment study has been completed.
    • Monitoring the HSE and QA/QC of Stage-2 development area Armor clearance activities.
  • Sub-surface Studies
    • Reservoir models have been prepared.
    • The PVT analysis for reservoirs fluid is in progress.
    • The well test analysis for reservoirs data are in progress.
    • The core analysis study for samples is in progress (Routine and SCAL).
  • Drilling Operations
    • Equipments and wellhead's valves for 8 wells have been procured.
  • Onshore Surface Facilities
    • Front end engineering and design (FEED) was completed.
    • FEED endorsed by Engineering, Procurement and Construction Management (EPCM) contractor.
    • Well-pads and access roads civil activities have been started.
    • Detailed engineering of Temporary Camp and Temporary Facilities (TCTF) were completed.
    • Construction of Temporary Camp and Temporary Facilities (TCTF) is in progress.


Well pad construction 


Well pad construction 





TCTF Construction

Contract Price and Duration :

  • Project duration is 40 month from effective date to reach the Extended Well Test milestone by establishing oil production level of 50,000 bbl/day and 52 month from effective date to reach the First Production milestone by establishing an oil production level of 150,000 bbl/day.
  • The buyback project contract price (capex) is 1,026 MMUSD.