Project Name :
Development Operations, Production Enhancement of Common Fields
in Salman Area (Salman Oil & Gas Fields Integrated Development
Project)
Location
:
Salman field is situated in the Persian Gulf, on the marine
border line with the United Arab Emirates (U.A.E.), 150 km south
of Lavan Island.
|
|
Scope
of work :
- 3-D
seismic, geological survey and reservoir modeling studies.
- Drilling
and conversion of 16 existing oil production wells into
wells with horizontal legs.
- Drilling
and conversion of 7 existing wells into water injection
wells.
- Drilling
one delineation gas well and completing the supplemental
work.
- Drilling
8 new gas wells and work-over an existing well.
- Construction of new gas lifting and production platforms and
bridges.
- Laying
new submarine infield flow-lines between the platforms.
- Construction
of two gas wellhead platforms, one
residential platform, one gas production and processing
platform, one flare platform and the connecting bridges.
- Implementing required modifications to enhance the
efficiency of existing offshore facilities.
- Construction and installation of gas compression facilities
on Sirri Island.
- Construction of a new 220 km, 30" export submarine gas
pipeline from the new gas processing platform to platform AP
of the United Arab Emirates via Siri Island.
|
Objectives:
-
Increasing crude oil production by 50,000 bpd.
-
Production of 500 million cubic feet per day of gas from the
gas reservoir.
Achievements:
Objectives:
Increasing crude oil production by 50,000 bpd
Status:
95% physical progress
-
-
Performed 3-D seismic Acquisition, Processing and
Interpretation
-
Full Field Reservoir Simulation Studies and Modeling
-
Reservoir Engineering Case Studies
-
-
Completing basic and detailed engineering, inspection,
procurement and purchase of required equipment, and
repairing or upgrading of the equipment and existing
tripod wellhead platforms.
-
-
-
Completing fabrication and installation of production
(PP3), 2SKB and 2SKC wellhead and flare platforms
(jackets and topsides) and connecting bridges.
-
Completing jackets fabrication and installation of gas
processing (KPP), residential (LQ3) and gas lifting (GLP)
platforms.
-
Completing laying of all submarine infield flow-lines and
export gas pipeline (Salman-Siri-AP route).
-
Fabrication of gas processing (KPP), residential (LQ3)
and gas lifting (GLP) topsides are in progress.
-
Construction and installation of Sirri Island gas
compression facilities is in progress.
|
|

|
Contract Price
and Duration :
Project commencement date is 9th August 2000 and project
duration for execution of oil and gas activities is 94 months.
The buyback project contract price (latest approved capex) is
902 MMUSD. |
|

KPP
Topside |

KPP Topside |
 |
 |
|
Sirri
Island Gas Compression Facilities
|
|